ECG Power Outage: Parts of Ashanti to Go Off 7:30am–5pm From November 16 to 18 as GRIDCo Upgrades Anwomaso–Ridge Line

ecg power outage parts of ashanti to go off 730am–5pm from november 16 to 18 as gridco upgrades anwomaso–ridge line

Parts of the Ashanti Region will be without electricity from 7:30am to 5:00pm daily from Monday, November 16 to Wednesday, November 18, 2026, the Electricity Company of Ghana (ECG) has announced. The three-day planned outage will allow the Ghana Grid Company Limited (GRIDCo) to continue upgrading the Anwomaso to Ridge Bulk Supply Point transmission line.

Communities and businesses listed in ECG’s notice include parts of Kaase, Guinness Ghana Limited, Fan Milk, Coca-Cola, Bomplex, Georgia, Abattoir, Boadi, Emina, Appiadu, Kokoben, Donyina and surrounding areas.

ECG issued the notice on Saturday, November 14, 2026, and said the work is part of ongoing efforts to improve power supply in the Ashanti Region.

The Ashanti exercise comes alongside separate maintenance outages in Tema and parts of the Eastern Region this week, after ECG carried out a similar round of cuts in Accra East and Tema from November 8 to 13.

ECG power outage in Ashanti: dates and times

The outage will run for three consecutive working days. Power is expected to go off at 7:30am and be restored by 5:00pm each day.

  • Monday, November 16, 2026: 7:30am – 5:00pm
  • Tuesday, November 17, 2026: 7:30am – 5:00pm
  • Wednesday, November 18, 2026: 7:30am – 5:00pm

That is about nine and a half hours without power each day, covering most of the working day.

Areas affected by the Ashanti power outage

ECG published one combined list of affected areas for the three days. It did not split the areas by day.

  • Parts of Kaase
  • Guinness Ghana Limited
  • Fan Milk
  • Coca-Cola
  • Bomplex
  • Georgia
  • Abattoir
  • Boadi
  • Emina
  • Appiadu
  • Kokoben
  • Donyina
  • Surrounding areas

Why GRIDCo is upgrading the Anwomaso–Ridge transmission line

According to ECG, GRIDCo is replacing the existing 364MVA single-circuit line between Anwomaso and the Ridge Bulk Supply Point with a modern double-circuit line.

The new line is rated at 2 x 488MVA, giving a combined capacity of 976MVA. ECG said the upgrade is meant to strengthen the transmission network and improve supply to customers in the affected parts of the region.

How the new line capacity compares

  • Old line: single circuit, 364MVA
  • New line: double circuit, 2 x 488MVA
  • Combined new capacity: 976MVA
  • Increase: 612MVA, or roughly 2.7 times the old capacity

A double-circuit line also means power can keep flowing on one circuit if the other develops a fault, which is one reason utilities use them on busy supply routes.

Other ECG outages this week: Tema and Eastern Region

ECG has also announced emergency maintenance in other areas this week. Parts of Tema, including U-Compound, CAC and surrounding areas, were scheduled to be off from 10:00am to 4:00pm today, Sunday, November 15.

On Tuesday, November 17, Kpong, Nuaso, Agormanya, St. Martin Hospital, Lower Manya Assembly, Kodjonya, Sawer, Agavenya, University Farm and surrounding areas are scheduled to be off from 10:00am to 3:00pm.

ECG said these interruptions are needed so engineers can carry out urgent repairs and system upgrades after recent faults on parts of the distribution network.

What the outage means for residents and businesses in Ashanti

Because the cuts fall within working hours, shops, cold stores, salons, welders and other businesses that depend on electricity are likely to feel the impact most. Several factories, including Guinness Ghana, Fan Milk and Coca-Cola, are named on the list.

ECG has asked customers in the affected areas to note the schedule and “make the necessary arrangements” before the power goes off. Residents may want to charge phones and power banks, store water and keep perishable food cold ahead of each day’s cut.

“The inconvenience that will arise as a result of this outage is deeply regretted,” ECG said in its notice.

What happens next

Power is expected to return by 5:00pm on Wednesday, November 18, when the scheduled three-day window ends. ECG has not said whether further outages will be needed to complete the GRIDCo project.

Customers can follow updates on ECG’s official website and social media pages, or contact their local ECG district office if power is not restored after the scheduled time.

Key details at a glance

  • Who announced: Electricity Company of Ghana (ECG)
  • Work by: Ghana Grid Company Limited (GRIDCo)
  • Dates: Monday, November 16 to Wednesday, November 18, 2026
  • Daily time: 7:30am to 5:00pm
  • Main areas: Kaase, Georgia, Abattoir, Boadi, Emina, Appiadu, Kokoben, Donyina and surrounding areas
  • Reason: Upgrade of the Anwomaso–Ridge line from 364MVA to 976MVA
  • Also this week: Outages in parts of Tema (November 15) and the Eastern Region (November 17)

FAQs

Which areas in Ashanti will have no light from November 16 to 18?

ECG lists parts of Kaase, Guinness Ghana Limited, Fan Milk, Coca-Cola, Bomplex, Georgia, Abattoir, Boadi, Emina, Appiadu, Kokoben, Donyina and surrounding areas.

What time will power go off and come back in Ashanti?

Power will go off at 7:30am and is expected to be restored by 5:00pm each day from Monday, November 16 to Wednesday, November 18, 2026.

Why is ECG cutting power in Kumasi this week?

The outage allows GRIDCo to upgrade the Anwomaso to Ridge Bulk Supply Point transmission line from a 364MVA single circuit to a 976MVA double circuit to improve supply in the region.

In summary, ECG customers in parts of the Ashanti Region should prepare for daily 7:30am–5:00pm power cuts from November 16 to 18, 2026, as GRIDCo works to more than double the capacity of the Anwomaso–Ridge transmission line, while parts of Tema and the Eastern Region face separate maintenance outages this week.