Obetsebi Lamptey–Pamprom Road to Reopen Between December 15 and 20 as GARID Drainage Works Hit 90%

obetsebi lamptey–pamprom road to reopen between december 15 and 20 as garid drainage works hit 90%

The stretch of road from the Obetsebi Lamptey Interchange to the Metro Mass area at Pamprom Junction in Accra is expected to reopen to motorists between December 15 and 20, 2026, after the first phase of the Kaneshie drainage project reached 90 per cent completion.

The update was given by Cephas Ofori, Project Manager of the Greater Accra Resilient and Integrated Development (GARID) Project, who said the contractors are working to open the road before the Christmas rush.

“We are targeting around the 15th to 20th of December,” Mr Ofori said on Channel One News, as reported by Graphic Online.

The westbound carriageway of the Dr Busia Highway, starting at Pamprom Junction, has been closed since September 7, 2026, to allow for the construction of a new underground drain at Kaneshie.

Obetsebi Lamptey–Pamprom road reopening date

GARID is targeting December 15 to 20 for the reopening of the Obetsebi Lamptey Interchange to Pamprom Junction section.

According to Mr Ofori, the remaining work on this section is backfilling and restoring the road pavement.

The timing is meant to ease congestion around the interchange during the busy Christmas season.

Kaneshie drainage works: what has been completed

The major construction on Phase One is done. Completed work includes:

  • Demolition along the affected stretch
  • Excavation for the new drain
  • Construction of the drain’s base walls
  • Installation of cover slabs

Work on Phase Two, covering the section from Pamprom Crossing to First Light, has already started.

How the new reopening date compares with the original plan

When the closure was announced in August, the first phase was scheduled to run until the end of November 2026, with Pamprom Junction expected to reopen in the first week of December.

  • Road closed: September 7, 2026
  • Original Phase One end: end of November 2026
  • Original Pamprom reopening target: first week of December 2026
  • New reopening target: December 15–20, 2026
  • Phase One progress: 90 per cent complete

Why the Kaneshie drain is being built

The works are part of the GARID Project, which aims to tackle flooding in Accra. The project was pushed forward after the June 29, 2026 floods that damaged property, disrupted livelihoods and claimed lives in Accra and coastal towns.

The old system of twin 1.2-metre-diameter pipes at Kaneshie is being replaced with a double-cell underground rectangular drain about 10 metres wide and 1.5 km long, running from Pamprom Junction towards First Light Junction.

The new channel links a recently completed drain on the Accra Academy campus to the existing main drain at Pamprom Junction. It adds to other flood-control efforts in the capital, including the Ghana Armed Forces’ operation to clear drains and waterways.

What it means for motorists in Accra

Drivers who have been diverted since September can expect the Obetsebi Lamptey–Pamprom stretch back in use just before Christmas, if the target holds.

GARID Communications Specialist Philip Dunyo said public education and alternative routes helped manage traffic, and that motorists largely complied with the arrangements, which prevented major gridlock.

Until the road reopens, the alternative routes announced for Phase One remain in place:

  • Awudome Cemetery Road
  • New Times Corporation – Awudome Roundabout route
  • Obetsebi Lamptey Interchange – Oblogo Traffic Light – Mataheko – First Light Junction

What happens next on the Dr Busia Highway

Reopening the Obetsebi Lamptey–Pamprom section does not end the works. The remaining westbound section from Kaneshie Station to First Light Junction was scheduled to stay closed until August 2027.

A further closure of the road from First Light to the Cocoa Clinic Roundabout is planned from September to the end of October 2027, affecting traffic from Kasoa, Odorkor, Russia Community and the Flamingo traffic light.

The public can reach GARID on the toll-free MTN lines 0800 800 900 and 0800 500 600.

Key details at a glance

  • Road: Obetsebi Lamptey Interchange to Metro Mass area, Pamprom Junction
  • Reopening target: December 15–20, 2026
  • Phase One progress: 90 per cent
  • Remaining work: backfilling and road pavement restoration
  • Closed since: September 7, 2026
  • Phase Two: Pamprom Crossing to First Light, already started
  • Project: Greater Accra Resilient and Integrated Development (GARID)

FAQs

When will the Obetsebi Lamptey to Pamprom road reopen?

GARID says the stretch is expected to reopen between December 15 and 20, 2026, once backfilling and pavement restoration are finished.

Why was the Dr Busia Highway at Kaneshie closed?

The westbound carriageway was closed on September 7, 2026, to build a new 10-metre-wide, 1.5 km underground drain under the GARID flood-control project.

Which roads can I use until Pamprom reopens?

Motorists can use Awudome Cemetery Road, the New Times–Awudome Roundabout route, or the Obetsebi Lamptey–Oblogo–Mataheko route to First Light Junction.

In summary, the Obetsebi Lamptey–Pamprom stretch closed since September is set to reopen between December 15 and 20, with Phase One of the Kaneshie drainage project 90 per cent done, while Phase Two works towards First Light continue into 2027.